Whenever a pipeline or appurtenance used in conjunction with the underground storage of natural gas in an underground reservoir is laid along a public road, it shall be placed as closely as practicable to the extreme outside edge of the right of way of the road.

(2)

Such pipeline or appurtenance shall not be located under or pass through or under any cemetery, church, college, schoolhouse, residence, business or storehouse, or through or under any building in this state, except by the consent of the owner thereof.

(3)

When cultivated lands are appropriated under ORS 772.615 (Condemnation for underground reservoirs), such pipelines shall be well buried underground, at least 20 inches under the surface, which shall be properly and promptly restored by the natural gas company unless otherwise consented to by the owner of the land.

(4)

When unimproved lands are appropriated under ORS 772.615 (Condemnation for underground reservoirs) and thereafter become cultivated or improved, such pipelines shall be buried by the natural gas company as provided in subsection (3) of this section, within a reasonable time after notice by the owner of such lands, or the agent of the owner, to the natural gas company or its agent. [1977 c.296 §10]

Source: Section 772.620 — Placement of pipeline facilities, https://www.­oregonlegislature.­gov/bills_laws/ors/ors772.­html.

772.010
Right of entry for survey of proposed right of way
772.015
Condemnation of lands for rights of way and necessary facilities
772.020
Condemnation of additional land for railway purposes
772.025
Approval of railroad crossing, intersection or connection
772.030
Condemnation of right of way through canyon or pass for joint use by railroads
772.035
Acquisition of water rights by corporations for canal, irrigation, domestic or stock purposes
772.040
Condemnation rights of pipe corporations
772.045
Right to cut timber and build aqueducts
772.050
Condemnation of riparian rights and for reservoirs
772.055
Condemnation procedure
772.060
Condemnation rights for change of grade or location of railway, canal or pipes
772.065
Appropriation of county road or property in lieu thereof by agreement with county court
772.070
Procedure on dispute between county and corporation
772.105
Authority to appropriate
772.205
Definitions for ORS 772.210 and 772.215
772.210
Right of entry and condemnation of lands for construction of service facilities
772.215
Appropriation of public lands
772.305
Condemnation of right of way for drainage or irrigation
772.310
Right to enlarge existing irrigation system
772.405
Condemnation by corporations for reduction of ores
772.410
Right of entry and condemnation by mining, quarrying and lumber corporations
772.415
Public benefit and use of facilities constructed under ORS 772.410
772.420
Condemnation for transportation of minerals
772.505
Definitions for ORS 772.505 to 772.520
772.510
Right of entry and condemnation by pipeline companies
772.515
Regulation concerning location of facilities
772.520
Resolution showing route and termini of pipeline
772.610
Definitions for ORS 772.610 to 772.625
772.615
Condemnation for underground reservoirs
772.620
Placement of pipeline facilities
772.625
Resolution showing proposed route and termini of pipeline
Green check means up to date. Up to date