2017 ORS 469.442¹
Procedure prior to construction of transmission line in excess of 230,000 volts
  • review committee

(1) Any person who proposes to construct a transmission line in excess of 230,000 volts capacity that is not otherwise under the jurisdiction of the Energy Facility Siting Council shall:

(a) Give public notice of the proposed action at least six months before beginning any process to obtain local permits required for the proposed transmission line. Notification shall be given:

(A) By publication once a week for four consecutive weeks in a newspaper of general circulation in the county or counties in which the transmission line is to be constructed; and

(B) To the governing bodies and planning directors of cities and counties which are within or partially within the project study area.

(b) Provide an opportunity for public comment on the proposed transmission line and conduct public meetings to review the proposal.

(c) Respond specifically and in writing to local concerns and recommendations regarding the proposed transmission line.

(2) The Director of the State Department of Energy shall establish a committee to include technical experts and members of the public to coordinate public review of a proposed transmission line under subsection (1) of this section when requested to do so by ordinance or resolution of the affected governing body.

(3) At the conclusion of the public review, the committee shall make a summary report to the affected governing body including public concerns and recommendations concerning the proposed transmission line.

(4) The scope of work and cost of conducting the review shall be negotiated between the State Department of Energy and the project sponsor. The negotiated cost shall be paid by the project sponsor.

(5) Subsections (1) to (4) of this section shall not apply to a person who proposes to construct transmission lines entirely within 500 feet of an existing corridor occupied by transmission lines with a capacity in excess of 230,000 volts. [1987 c.200 §2; 1993 c.569 §18]

Notes of Decisions

The Energy Facility Siting Council failed to adopt sufficient standards concerning financial ability, qualifica­tions to construct and operate, and power needs. Marbet v. Portland General Electric, 277 Or 447, 561 P2d 154 (1977)

Atty. Gen. Opinions

Permits, licenses and certificate require­ments for “executed site certificate,” (1974) Vol 37, p 103; appoint­ment and reappoint­ment of Council members, (1979) Vol 39, p 619

Law Review Cita­tions

13 WLJ 499 (1977); 57 OLR 334 (1978)

1 Legislative Counsel Committee, CHAPTER 469—Energy; Conservation Programs; Energy Facilities, https://­www.­oregonlegislature.­gov/­bills_laws/­ors/­ors469.­html (2017) (last ac­cessed Mar. 30, 2018).
 
2 Legislative Counsel Committee, Annotations to the Oregon Revised Stat­utes, Cumulative Supplement - 2017, Chapter 469, https://­www.­oregonlegislature.­gov/­bills_laws/­ors/­ano469.­html (2017) (last ac­cessed Mar. 30, 2018).
 
3 OregonLaws.org assembles these lists by analyzing references between Sections. Each listed item refers back to the current Section in its own text. The result reveals relationships in the code that may not have otherwise been apparent.