2017 ORS 279C.660¹
Compensation when contract terminated due to public interest

When a public contract is terminated by mutual agreement, provision shall be made for the payment of compensation to the contractor. In addition to a reasonable amount of compensation for preparatory work and for all costs and expenses arising out of termination, the amount to be paid to the contractor:

(1) Shall be determined on the basis of the contract price in the case of any fully completed separate item or portion of the work for which there is a separate or unit contract price; and

(2) May, with respect to any other work, be a percent of the contract price equal to the percentage of the work completed. [2003 c.794 §162]

1 Legislative Counsel Committee, CHAPTER 279C—Public Improvements and Related Contracts, https://­www.­oregonlegislature.­gov/­bills_laws/­ors/­ors279C.­html (2017) (last ac­cessed Mar. 30, 2018).
 
2 OregonLaws.org contains the con­tents of Volume 21 of the ORS, inserted along­side the per­tin­ent statutes. See the preface to the ORS An­no­ta­tions for more information.
 
3 OregonLaws.org assembles these lists by analyzing references between Sections. Each listed item refers back to the current Section in its own text. The result reveals relationships in the code that may not have otherwise been apparent.