Extension and compensation when work suspended
If a public contract is not terminated but work under the contract is suspended by an order of a contracting agency for any reason considered to be in the public interest other than a labor dispute or any third-party judicial proceeding relating to the work other than a suit or action filed in regards to a labor dispute, the contractor is entitled to a reasonable extension of the contract time and reasonable compensation for all costs resulting from the suspension plus a reasonable allowance for overhead with respect to such costs. [2003 c.794 §161]
1 Legislative Counsel Committee, CHAPTER 279C—Public Contracting - Public Improvements and Related Contracts, https://www.oregonlegislature.gov/bills_laws/Archive/2007ors279C.pdf (2007) (last accessed Feb. 12, 2009).
2 OregonLaws.org contains the contents of Volume 21 of the ORS,
inserted alongside the pertinent statutes.
See the preface to the ORS Annotations for more information.
3 OregonLaws.org assembles these lists by analyzing references between Sections. Each listed item refers back to the current Section in its own text. The result reveals relationships in the code that may not have otherwise been apparent. Currency Information
3 OregonLaws.org assembles these lists by analyzing references between Sections. Each listed item refers back to the current Section in its own text. The result reveals relationships in the code that may not have otherwise been apparent. Currency Information